Installation method of vertical pipeline pump

From:YangTze River Time:2026/9/23 21:34:41

The vertical pipeline pump has a vertical structure, with the same inlet and outlet diameters and located on the same center line. It can be installed in the pipeline like a valve, equipped with installation feet to enhance its stability. It has an attractive appearance, occupies a small area, requires low construction investment, and does not need to establish a separate pump room. There are many types of vertical pipeline pumps, such as ISG vertical pipeline pump, IHG stainless steel vertical pipeline pump, GDL vertical multi-stage pipeline pump, and shielded pipeline centrifugal pump, etc. Now, let's introduce the installation method and installation diagram of the vertical pipeline pump.

vertical pipeline pump

Installation method of vertical pipeline pump

1. If the pipeline is not installed, first install the water pump, draw the diagram based on the centerlines of the pump's inlet and outlet, and then install the pipeline.
2. If the pipeline has been installed, first ensure that the inlet and outlet of the pipeline are on the same center line, and install the support frame near the inlet and outlet of the pipeline.
3. Connect the vertical centrifugal pump with the inlet and outlet pipeline using flanges, and place a hard object on the pump's base to prevent damage to the pump body and pipeline. Mark the diagonal lines and center positions of the four bolt holes on the pump base with a marker pen.
4. Measure the height between the prefabricated foundation and the pump base, and leave a reasonable height for the shock absorber or shock pad.
5. Remove the pump and drill holes with an impact drill. According to the diagonal lines and center distances of the four bolt holes of the pump, pre-drill expansion screws or bolts.
6. Clean the grease and dirt on the base of the vertical pipeline pump, and place the base on the foundation.
7. Check the levelness of the vertical pipeline pump base with a level instrument.
8. Pour cement into the base of the vertical pipeline pump and the holes of the foundation bolts.
9. After the cement dries, check whether the base of the vertical pipeline pump and the holes of the foundation bolts are loose. Tighten the foundation bolts appropriately and recheck the levelness.
10. Clean the support plane of the vertical pipeline pump base, the plane of the pump feet and the motor feet, and install the vertical pipeline pump and the motor on the base.
11. Check and adjust the coincidence degree of the center line of the vertical pipeline pump and the motor shaft, check whether the center line of the pump shaft and the motor shaft are consistent, the difference in the outer circles of the two coupling should not exceed 0.1 millimeters, and use a thin sheet to adjust them to be concentric, leave a gap of 2-3 millimeters between the end faces of the two couplings.


The above is our summary of the installation method for vertical pipeline pumps. In conclusion, the correct installation and use of vertical pipeline pumps can ensure the safe operation of the equipment, reduce some unnecessary losses, and after installation, attention should also be paid to maintenance and upkeep during the subsequent daily use.